Clarification No. 2
Date: 2015/5/14
Bid No.:CMIT-GED-10.53-150083
Project Title: Additional materials for 90 well upgrading
Subject: Clarification to change the specifications of the ground pedal
Dear Bidders,
Due to further consideration by Company, the gratings (Item24) to be procured in this bidding is clarified as follows:
1. Dimension introduction:
The new dimension of the ground pedal must be based on the detail design in attachment 1-1 and attachment 1-2;
2. Anticorrosive and painting color introduction:
2.1 The grating plate must be done HDG(hot dip galvanizing)treatment;
2.2 The grating plate must be painted in silver-white color paint;
3. Notes:
One set of grating include the grating shown in attachment 1-1 and attachment 1-2;
For drawings, please download the relevant document in below website:
user name: contractor
pass word: contractor
To facilitate the cooperation, please do not hesitate to contact with Company if there is any doubt.
Thanks for your understanding and cooperation.
Regards!
_________________________
Deputy Project Manager of civil work and gathering pipeline project
CNOOC Iraq Limited