BULLETIN No.3

         Date: August 2nd, 2015

Ref: PRT-2015- 0186

No.: CMIT-PRT-10.30-150129

Project Title: Supplementary Completion Tools

Subject: Technical Clarification Response

 

Dear potential Bidders,

                              

In respect of received Technical Clarification request of tender No CMIT-PRT-10.30-150129; please find the Technical clarification response per attached “Appendix 1”.        

 

 

NOTE:

1.      All documents of ITT and bulletins of the Tender can be downloaded as the link below,

http://www.cnoociraq.com/share/page/site/BiddingDoc/documentlibrary#filter=path%7C/150129%2520ITT%2520for%2520Supplement%2520Completion%2520Tools&page=1

·                    Username: contractor

·                    Password: contractor

 

2.      Contact persons of the Tender:

·         Attention: Ms. Ma Xuemei / Ms. Rim Issa

·         Email: maxm3@cnoociraq.com / rimissa@cnoociraq.com

  • Address: 7WB-3100 ,Dubai Airport Free Zone,Dubai, UAE.

·         Tel: +971 (0)4 2108 166    / +971 (0)4 2108 170

 

Thanks for your understanding and cooperation.

 

Regards

_________________________

Mr. Ma Peixin

Manager of Contracts & Procurement Department

CNOOC Iraq Limited


Appendix 1

 

No.

Bidder's Clarification Questions

Customer's Response

1

Please confirm if T-95 material is a firm requirement for completion items as defined in ITT or tenderer can propose alternate material for the same

Please conform to the specification stipulated in scope of supply, ITT SECTION 3 “TECHNICAL REQUIREMENTS AND SPECIFICATION”

2

Please confirm if standard 13-Cr/9-Cr Material is Acceptable instead of T95 for line item 4.2, 5.2, 6.2 & 7.2 mentioned in the RFQ. As these plugs/test tools will be installed downhole for short period of time.

Please conform to the specification stipulated in scope of supply, ITT SECTION 3 “TECHNICAL REQUIREMENTS AND SPECIFICATION”

3

In the section 3 of the ITT, there was no mention about the size and poundage of the 5-1/2” casing. Please clarify as to where this information was published?

The following are found and there is no mention about 5-1/2” casing. In addition, appreciate if a well schematic can be provided for clarity.”

Please refer to cope of supply, items 2.1, ITT SECTION 3 “TECHNICAL REQUIREMENTS AND SPECIFICATION”